Learn about the ongoing Public Works and Facilities repair projects to county roads, right of ways and facilities from damage caused by Hurricane Ian.
Riverside Boat Ramp Replacement
Last Updated: 05/10/2024 Category: Parks And Recreation Current Phase: Design Development
As part of the CMP, Community Services is conducting structural assessments on all piers, boardwalks, seawalls and boat ramps; through this assessment process it was bought to CS attention that Riverside Boat Ramp provides immediate safety concerns. During the site analysis the engineer determined the ramp could not be repaired in place; this project will be to design a replacement ramp that alleviates the safety issues.
William R Gaines Jr. Veterans Memorial Park Phase II
Last Updated: 05/10/2024 Category: Parks And Recreation Category: Sales Tax Funded Current Phase: Planning and Project Approval
William R. Gaines Jr. Veterans Memorial Park phase II design and construction.Bayshore Live Oak Park - West Fishing Pier
Last Updated: 05/10/2024 Category: Parks And Recreation Current Phase: Planning and Project Approval
Total replacement of the western fishing pier at Bayshore Live Oak Park.Last Updated: 05/10/2024 Category: Parks And Recreation Current Phase: Planning and Project Approval
Park master plan for Lake Betty Park
Phase 1 of the Master Plan includes a toddler playspace, ropes/ninja style athletic course, picnic pavilions, walking paths, and an improved parking lot.
Last Updated: 05/10/2024 Category: Parks And Recreation Category: Sales Tax Funded Current Phase: Planning and Project Approval
GC Herring Phase I design and construction. Redevelopment of the park will include necessary amenities for a community park as identified in the Parks and Recreation master Plan.Port Charlotte Beach Recreation Center
Last Updated: 05/10/2024 Category: Parks And Recreation Category: Sales Tax Funded Current Phase: Design Development
Design a new recreation center that will serve the current needs of rental venue for events, as well as community facilities for sailing and regatta events.Landfill Scale House (Zemel Road)
Last Updated: 05/10/2024 Category: County Facilities Current Phase: Turnover and Closeout
The scale house at the Zemel Road Landfill is currently a trailer nearing end of expected usable lifecycle. Additionally, not compliant with the County's Ordinance of not utilizing trailers as permanent operations. The project would move the physical location of the scale house and its ancillary functions of a convenience center and household hazardous waste. The project will also streamline the flow and control of traffic in and out of the landfill.
Last Updated: 05/10/2024 Category: Parks And Recreation Current Phase: Planning and Project Approval
Creation of a master plan through the park design process and phase 1 development.Harold Avenue Generator Mitigation Grant
Last Updated: 05/10/2024 Current Phase: Turnover and Closeout
This Mitigation Grant funded project will provide a permanent backup generator and enclosure for the Harold Avenue Recreation Center.